FULL LIST: Seven States Set To Experience Six-week Power Outage Over Grid Upgrade

Nigerian Independent System Operator (NISO) has announced that seven states will face weeks of disrupted power supply following a scheduled outage on the Jos–Gombe 330kV transmission line.

The outage, announced by NISO in a public notice on Thursday, is set to run from April 9 to May 22, 2026.

According to the operator, the disruption will occur weekly from Thursday to Sunday between 9:00 am and 6:00 pm to enable the installation of Optical Ground Wire fibre optic infrastructure along the transmission corridor.

The seven states include Plateau, Gombe, Bauchi, Borno, Adamawa, Taraba, and Yobe

The agency explained that the upgrade is part of ongoing efforts to modernise the national grid and enhance its operational efficiency through improved Supervisory Control and Data Acquisition systems, Energy Management Systems, and telecommunications capabilities.

Also Read:  Corps Liaison Officer Accused Of Ass@ulting Two Female NYSC Members

“The outage is necessary to facilitate the installation of Optical Ground Wire fibre optic infrastructure along the line,” the notice stated, adding that the project is expected to strengthen real-time monitoring, fault detection, load balancing, and overall energy delivery in the region.

Despite assurances that alternative supply arrangements will be put in place, the operator warned that consumers in the affected states should expect reduced electricity supply during the outage periods.

It noted that electricity will be routed through available 132kV transmission lines, but capacity limitations may result in service disruptions across feeders and substations.

“Due to inherent network constraints and limited capacity on these lines, customers may experience reduced power supply and service limitations within the stated outage window,” the statement added.

Also Read:  Oyo Govt Faults Adelabu’s Claim On Power Projects 

The system operator said it is working closely with stakeholders, including distribution companies and the Transmission Company of Nigeria, to minimise the impact of the outage.

The development underscores persistent challenges in Nigeria’s power transmission network, where infrastructure upgrades often lead to temporary disruptions due to limited redundancy and capacity constraints.

However, the agency maintained that the project would deliver long-term benefits, including improved electricity reliability, faster fault response, enhanced grid coordination, and better integration of generation and load data.

It added that the fibre optic installation would also strengthen the telecommunications backbone required for modern power system operations.

While apologising for the inconvenience, the operator appealed for public understanding, noting that the upgrade is critical to achieving a more stable and efficient electricity supply across the affected region.

Also Read:  Uninterrupted Electricity Supply Takes Off In Ibadan

WARNING: If You Are Not 18+, Don’t Click The Link Below 👇🫣 

https://omg10.com/4/8902554

https://wrathful-piano.com/zBn8jS

Did you want to monetize your website, join MONETAG or ADSKEEPER and start earning 

Please don’t forget to “Allow the notification” so you will be the first to get our gist when we publish it.

Drop your comment in the section below, and don’t forget to share the post.

Never Miss A Single News Or Gist, Kindly Join Us On WhatsApp Channel:
https://whatsapp.com/channel/0029Vad8g81Eawdsio6INn3B

Telegram Channel:
https://t.me/gistsmateNG

Posted in NEWS and tagged , .

Leave a Reply

Your email address will not be published. Required fields are marked *